Ivy Street Sidewalk Project
From a $50,000 grant obtained by the Village, we are replacing approx. 800 lineal feet of sidewalk on the 200 block of W. Ivy Street to tie into the new sidewalks the NY State DOT installed as part of the Washington St. project, as well as replacing the sidewalks around the bathrooms and the lodge at Eyer Park. Work for this began on Thursday April 23rd and should be completed by the end of next week.
6/29/2009 - Update
All work for this project has been succussfully completed and all areas restored. The Village is in the process of receiving the grant money for reimbursement for this project. |
|